skip to Main Content
November Forecast of Work Activity

The activities listed below are scheduled to continue and/or begin in November. The approximate locations and work hours for these activities are provided in Info Bulletin No. 2 (October 2018).

Nuuanu Ave. between School St. & Wyllie St.

  • Underground relocations of water lines at the intersections of Kuakini St., Bates St., and Judd St., and at various locations between Kuakini St. and Pauoa Rd.

Wyllie St. between Burbank St. & Nuuanu Ave.

  • Surveying and potholing to confirm locations of existing underground utilities at various locations.

Pali Hwy. between Wyllie St. & Dowsett Ave.

  • Setup of project staging areas at various locations in the town bound shoulder lane from Dowsett Ave. to Wyllie St.
  • Surveying and potholing to confirm locations of existing underground utilities at various locations.

Pali Hwy. between Dowsett Ave. & Nuuanu Pali Dr.

  • Surveying and potholing to confirm locations of existing underground utilities at various locations.

Dowsett Ave.

  • Surveying and potholing to confirm locations of existing underground utilities at various locations.
Overall Project Schedule and Work Hours

The contract Notice-To-Proceed was issued July 9, 2018. The substantial completion deadline is June 7, 2020.  All new sewer pipelines need to be installed and able to transport wastewater by the substantial completion date.  Various construction closeout activities (e.g. pavement and landscaping restoration, punch-list work, etc.) are not contractually required to be completed by June 2020 and may continue for several months after substantial completion is achieved.  An aggressive schedule is required to substantially complete the project by June 2020.  Construction crews will need to work at many concurrent locations throughout the project.  Crews may need to work some weekends and holidays, and in some location crews may need to work night shifts.

Traffic Updates

Traffic Updates for November

Daytime construction work will require relatively isolated lane closures at several locations on Nuuanu Ave., Wyllie St., Dowsett Ave., and Pali Hwy.  Access to driveways will be maintained via right turn motions from the travel lanes fronting them; however, access to some driveways via left turn motions may not be available due to required traffic control configurations.  Short term detours may be needed for work near Wyllie St. and Dowsett Ave.  Please observe the posted construction traffic signage.  Thank you for your patience!

Project Hotline: (808) 793-7184

Back To Top