January / February Forecast of Work Activity

The activities listed below are scheduled to continue and/or begin in January and/or February. The approximate locations and work hours for these activities are provided in Info Bulletin No. 5.

Nuuanu Ave. between School St. & Wyllie St.

  • Underground relocations of water and gas lines at the intersections of Kuakini St., Pauoa Rd., and Bates St.
  • Installation of new sewer pipelines and manholes, including trench excavation and trench restoration, at various locations between School St. and Judd St.

Pali Hwy. between Coelho Way and Ahi Place.

  • Construction of guided bore pipe installation shafts at various locations in the town bound shoulder lane between Coelho Way and Ahi Place.